Results of the Ist half of 2021 for the overhaul of the track

Let's sum up the results of the 1st half of 2021 on the overhaul of the track of Temirzhol zhundeu LLP:

With the plan of 75.783 km, the fulfillment was 122, 423 km (160%)

Ballasting was carried out with track crushed stone in the volume of 334 thousand m3.

Inventory rails were replaced with new long-length jointless strings in the amount of 55.71 km.

We thank all our field workers for their work and professionalism!

Despite the difficulties in a pandemic, all the tasks and goals have been exceeded!